Sunday, June 3, 2012

● Meeting hall construction update as of May 25, 2012

1. The power transformer was finally installed on May 24. All the lights at the lobbies, main sanctuary, and the parking lot were turned on for the first time using the permanent electric power. Fire alarm testing was conducted on May 25 and verification by the fire department will be done on May 29.

2. Plumbing fixtures have been installed on the baptismal tub, shower stalls and washrooms.

3. Onsite landscaping is near completion. Offsite works are 100% complete except for the final asphalt paving schedule one year from now.

4. Remaining work on the elevator will be finished by the final week of May.

5. Deficiencies in the roofing and flooring are being checked and remedied.

6. The meeting hall is due for city inspection and approval for occupancy after all paper works are completed. We must pray for all the construction and administrative processes to be concluded by the end of May and for the building to be turned over to us by early June. 


Offering for the meeting hall construction (as of May 20, 2012)

Offering Goal
Current Accumulated Offerings
($1.35 M Loan from LM churches)

Current Disbursement
Current Balance
($1.35M Loan from LM churches)
$4,500,000
$3,559,062 /
$4,909,062
Project Fund
Security Deposit
Total Expenditure
$1,098,045 /
$251,955
$4,447,107
$210,000
$4,657,107
Percentage of our Goal Achieved at present
Current Deficit
79.09%
$940,938