● Meeting hall construction update as of April 12, 2012


1. Floor tiles are now being installed in the kitchen. Other areas to be tiled are the front and central lobbies and all the washrooms. 
2. At the main sanctuary, the six acoustic clouds have been attached to the ceiling. T-bar ceiling frames and panels, LED light fixtures, and airconditioning diffusers are now being installed. Doors and window glass on the side adjoining the central lobby will be mounted starting next week. 
3. The elevator is still being installed, with the machine already relocated to the ground floor beside the church office. 
4. At the site meeting on April 12, we were informed that our general contractor had to shuffle superintendents because of a serious injury to one, 
and the superintendent on our project will be assigned to take his place. We need to pray for the safety and efficiency of all the working crews to 
keep the momentum going smoothly, so that despite changing circumstances, our building can be completed according to plan and schedule. 


 Offering for the meeting hall construction, as of April 08, 2012




Offering Goal
Current Accumulated Offerings
($1.35 M Loan from
Lower Mainland churches)

Current Disbursement
Current Balance
($1.35M Loan from
Lower Mainland churches)
$4,500,000
$3,438,797 /
$4,788,797
Project Fund
Security Deposit
Total Expenditure
$599,802 /
$750,198
$3,828,599
$210,000
$4,038,599
Percentage of our Goal Achieved at present
Current Deficit
76.41%
$1,061,203