● Meeting Hall Construction Update as of January 15, 2012

  1. Various trade works are progressing well (electrical & plumbing rough-ins and fire protection piping, etc.)

  2. The following works are completed:
    • Benches, ramp retaining walls & planters
    • Garbage enclosure & landscape fencing




A view from the main sanctuary looking toward the balcony




Offering for the meeting hall construction, as of January 15, 2012
 
Offering Goal
Current Accumulated Offerings
Current Disbursement
Current Balance
$4,500,000 (CAD)
$3,180,946 (CAD)
Project Fund
Security Deposit
Total Expenditure
$541,057 (CAD)
$2,456,889
$210,000
$2,223,365 (CAD)
Percentage of our Goal Achieved at present
Current Deficit
70.69%
$1,319,054 (CAD)