1. The painting work is proceeding at a faster rate with more painters on the job.
2. T-bar ceilings have been installed in all the ground-floor rooms.
3. The washrooms are being tiled and fitted with plumbing fixtures.
4. LED lights in the main sanctuary were turned on for the first time on Wednesday morning.
5. Wall plates for appliances and audio and data equipment are being installed.
6. Telus crew came on Thursday morning to transfer all phone-related cables
to the new Hydro pole.
7. The parking lot is nearing completion with most of the paving stones
already installed.
8. Planter boxes are being placed along the promenade fronting the building.
9. Work on the elevator is still going on, with electric power supplied by a generator.
10. Permanent power still awaits the BC Hydro crew to come and install.
10. Permanent power still awaits the BC Hydro crew to come and install.
No comments:
Post a Comment