1. Floor tiles are now being installed in the kitchen. Other areas to be tiled are the front and central lobbies and all the washrooms.
2. At the main sanctuary, the six acoustic clouds have been attached to the ceiling. T-bar ceiling frames and panels, LED light fixtures, and airconditioning diffusers are now being installed. Doors and window glass on the side adjoining the central lobby will be mounted starting next week.
3. The elevator is still being installed, with the machine already relocated to the ground floor beside the church office.
4. At the site meeting on April 12, we were informed that our general contractor had to shuffle superintendents because of a serious injury to one,
and the superintendent on our project will be assigned to take his place. We need to pray for the safety and efficiency of all the working crews to
keep the momentum going smoothly, so that despite changing circumstances, our building can be completed according to plan and schedule.
Offering for the meeting hall construction, as of April 08, 2012
Offering
Goal
|
Current
Accumulated Offerings
($
Lower Mainland churches)
|
Current
Disbursement
|
Current
Balance
($
Lower Mainland churches)
|
||
$4,500,000
|
$3,438,797
/
$4,788,797
|
Project Fund
|
Security
Deposit
|
Total
Expenditure
|
–$599,802
/
$750,198
|
$3,828,599
|
$210,000
|
$4,038,599
|
|||
Percentage of our Goal Achieved at present
|
Current Deficit
|
||||
76.41%
|
$1,061,203
|