1. We had a meeting at the site with both the present and
the new superintendents to discuss the
latest work progress.
latest work progress.
2. Tiles are now being installed in the washrooms. The
plumbing fixtures will be installed starting next week.
3. The exterior walls are now being painted with the primer
coating.
4. LED lighting fixtures are being installed in the main
sanctuary.
5. Paving stones on
the parking lot and the walkway are nearing completion.
6. Kitchen
appliances, washing machine and dryer need to be ordered soon.
7. Audio
equipment will be ready for installation starting next Monday.Offering for the meeting hall construction, as of April 15, 2012:
Offering
Goal
|
Current
Accumulated Offerings
($
Lower Mainland churches)
|
Current
Disbursement
|
Current
Balance
($
Lower Mainland churches)
|
||
$4,500,000
|
$3,445,707
/
$4,795,707
|
Project Fund
|
Security
Deposit
|
Total
Expenditure
|
–$786,769
/
$563,231
|
$4,022,476
|
$210,000
|
$4,232,476
|
|||
Percentage of our Goal Achieved at present
|
Current Deficit
|
||||
76.57%
|
$1,054,293
|