Wednesday, April 25, 2012

● Meeting hall construction update as of April 20, 2012

1. We had a meeting at the site with both the present and the new superintendents to discuss the
     latest work progress.                           
2. Tiles are now being installed in the washrooms. The plumbing fixtures will be installed starting next week.
3. The exterior walls are now being painted with the primer coating.
4. LED lighting fixtures are being installed in the main sanctuary.
5. Paving stones on the parking lot and the walkway are nearing completion.        
6. Kitchen appliances, washing machine and dryer need to be ordered soon.
7. Audio equipment will be ready for installation starting next Monday.


Offering for the meeting hall construction, as of April 15, 2012:



Offering Goal
Current Accumulated Offerings
($1.35 M Loan from
Lower Mainland churches)

Current Disbursement
Current Balance
($1.35M Loan from
Lower Mainland churches)
$4,500,000
$3,445,707 /
$4,795,707
Project Fund
Security Deposit
Total Expenditure
$786,769 /
$563,231
$4,022,476
$210,000
$4,232,476
Percentage of our Goal Achieved at present
Current Deficit
76.57%
$1,054,293