Wednesday, April 11, 2012

● Meeting hall construction update as of April 5, 2012

1.   The conduits for the electric lines connecting to the pole are being cleaned before electricity can
      be connected.
2.   Two trellises are being installed, one with a glass canopy over the front entrance, and a second 
      one, an open frame on the side facing Brown Road.
3.   Paving stones are being laid on the parking zones.
4.   Painting of the interior will continue for the next two weeks.       

Trellises being installed on the exterior (April 5, 2012)

Offering for the meeting hall construction, as of April 01, 2012 


Offering Goal
Current Accumulated Offerings
($1.35 M Loan from
Lower Mainland churches)

Current Disbursement
Current Balance
($1.35M Loan from
Lower Mainland churches)
$4,500,000
$3,432,162 /
$4,782,162
Project Fund
Security Deposit
Total Expenditure
$606,437 /
$743,563
$3,828,599
$210,000
$4,038,599
Percentage of our Goal Achieved at present
Current Deficit
76.27%
$1,067,838
    