- The roofing system on the main portion of the building is now complete.
- The roofing for the northwest portion, which will be fitted with glass panels, is scheduled for the coming week.
- The aluminum frames for the windows are being installed.
- A cedar fence is now being erected on the south property line. Another section of fence will be placed on the east property line behind the building.
- The metal decking for the second floor is now complete and concrete pouring will begin on Monday, Dec. 19.
- The parking lot is now being leveled with sand and gravel.
Latest photo of the meeting hall's front lobby, showing the main stairs leading to the second floor. (Dec. 16, 2011) |
Offering Goal | Current Accumulated Offerings |
Current Disbursement | Current Balance | ||||||||
$4,500,000 (CAD) | $3,042,646 (CAD) | ProjectFund | Security Deposit | Total Expenditure | $333,989 (CAD) | ||||||
$2,120,657 (CAD) | $588,000 (CAD) | $2,708,657 (CAD) | |||||||||
Percentage of our Goal Achieved at present | Current Deficit | ||||||||||
67.61% | $1,457,354 (CAD) |