- We held a site meeting last Wednesday to discuss the work progress. 
- The second floor and stairs are being installed and cement pouring will be done in one operation. 
- The following works and installations are in progress:
- A cedar fence is now being erected on the south property line. Another section of fence will be placed on the east property line behind the building.
- The metal decking for the second floor is now complete and concrete pouring will begin on Monday, Dec. 19. 
- The parking lot is now being leveled with sand and gravel.
| Offering Goal | Current Accumulated Offerings | Current Disbursement | Current Balance | ||||||||
| $4,500,000 (CAD) | $3,011,181 (CAD) | ProjectFund | Security Deposit | Total Expenditure | $340,505 (CAD) | ||||||
| $2,082,676 (CAD) | $588,000 (CAD) | $2,670,676 (CAD) | |||||||||
| Percentage of our Goal Achieved at present | Current Deficit | ||||||||||
| 66.91% | $1,488,819 (CAD) | ||||||||||
 