Friday, December 16, 2011

● Meeting Hall Construction Update as of December 9, 2011

  1. We held a site meeting last Wednesday to discuss the work progress.

  2. The second floor and stairs are being installed and cement pouring will be done in one operation.

  3. The following works and installations are in progress:

    1. A cedar fence is now being erected on the south property line. Another section of fence will be placed on the east property line behind the building.
    2. The metal decking for the second floor is now complete and concrete pouring will begin on Monday, Dec. 19.
    3. The parking lot is now being leveled with sand and gravel.


Offering for the meeting hall construction, as of
December 09, 2011

 
Offering Goal Current Accumulated
Offerings
Current Disbursement Current Balance
$4,500,000 (CAD) $3,011,181 (CAD) ProjectFund Security Deposit Total Expenditure $340,505 (CAD)
$2,082,676 (CAD) $588,000 (CAD) $2,670,676 (CAD)
Percentage of our Goal Achieved at present Current Deficit
66.91% $1,488,819 (CAD) 