● Meeting Hall Construction Update as of December 23, 2011

  1. The second floor concrete slab has been completed.

  2. The roofing is almost complete. Flashing along the parapet walls and around the roof-top air-conditioning units will be done later.

  3. The window glass panes are now being installed.

  4. Steel studs are being installed on the walls of the main meeting area. The drywall will be attached to these studs later.

  5. The construction committee had a meeting on Dec. 22 to finalize the audio design plan. A meeting with the electrical contractor is planned for the first week of January 2012.





Offering for the meeting hall construction, as of
December 23, 2011

  
Offering Goal Current Accumulated Offerings Current Disbursement Current Balance
$4,500,000 (CAD) $3,143,181 (CAD) ProjectFund Security Deposit Total Expenditure $136,069 (CAD)
$2,419,112 (CAD) $588,000 (CAD) $3,007,112 (CAD)
Percentage of our Goal Achieved at present Current Deficit
69.85% $1,356,819 (CAD) 