- The second floor concrete slab has been completed.
- The roofing is almost complete. Flashing along the parapet walls and around the roof-top air-conditioning units will be done later. 
- The window glass panes are now being installed.
- Steel studs are being installed on the walls of the main meeting area. The
drywall will be attached to these studs later. 
- The construction committee had a meeting on Dec. 22 to finalize the audio design plan. A meeting with the electrical contractor is planned for the first week of January 2012.
| Offering Goal | Current Accumulated Offerings | Current Disbursement | Current Balance | |||||||
| $4,500,000 (CAD) | $3,143,181 (CAD) | ProjectFund | Security Deposit | Total Expenditure | $136,069 (CAD) | |||||
| $2,419,112 (CAD) | $588,000 (CAD) | $3,007,112 (CAD) | ||||||||
| Percentage of our Goal Achieved at present | Current Deficit | |||||||||
| 69.85% | $1,356,819 (CAD) | |||||||||


 