August 24, 2011:
• From August 12 to August 24, the contractor for site services has performed 100% of the sanitary sewer
works and about 90% of the storm sewer works. Progress billing of $195,000 is due and payable this
month.
• By September 16, the site services will have been fully completed and the balance of $240,000 will be due
and payable at that time.
• The design of the main meeting hall requires much study and consideration for a suitable acoustic
environment that optimizes and balances sound absorption and transmission.
• Please continue to pray for the meeting hall to be designed and built for the most effective control of
outside noise from air and road traffic, for the most pleasant conveying of interior sound from speaking and
singing, and for the timely progress of the construction and for its completion by June 1, 2012.
Information regarding the offering for the meeting hall construction, as of August 21, 2011:
Offering Goal | Current Accumulated Offerings | Current Disbursement | Current Balance |
---|---|---|---|
$4,500,000 (CAD) | $2,619,499 (CAD) | $1,264,472 (CAD) | $1,355,027 (CAD) |
Percentage of our Goal Achieved at Present | Current Deficit | ||
58.21% | $1,880,501 |
August 19, 2011: |
---|
• The sewer construction started on Aug. 12 and is expected to be completed by the middle of September. |
• The excavation and foundation work that began on Aug. 16 will last until the first week of October with the pouring of the concrete slab. |
• From the second week of October until the fourth week of November, the concrete tilt panels will be prepared, poured, cured, and erected. |
• The structural steel, metal decking, and roofing will be installed from November until the end of this year. |