Drainage pipes are now being installed along the south and east property lines.
Please see the attached file for the updated construction schedule. June 1, 2012 is the new target date for occupancy. Praise the Lord! The individual prayers of the saints and the corporate prayers of the churches will make this a reality at the appointed time! ● The attached file for the updated construction schedule>>
Information regarding the offering pledges for the meeting hall construction:
As of August 07, 2011:
Offering Goal
|
Current Accumulated Offerings
|
Current Disbursement
|
Current Balance
|
$4,500,000 (CAD)
|
$2,530,209 (CAD)
|
$1,227,872 (CAD)
|
$1,302,337 (CAD)
|
Percentage of our Goal Achieved at present
|
Current Deficit
| ||
56.23%
|
$1,969,791 (CAD)
|
News Update on the Meeting Hall Construction:
As of August 12, 2011:
1. The lock-blocks have been laid as permanent retaining walls along the south and the east property lines.
2. The storm sewer construction along Brown Road started last week. The stretch of road fronting our property is a temporary no-parking zone from Monday to Friday, 7 a .m. to 5 p.m. Saints who wish to see the site may do so from the school playground on the east side.
3. This week the contractor will start drainage work on site.
4. Clearing of trees and shrubs north of the site will be scheduled within this month.
5. Work on the footings for the columns of the building is scheduled to begin after the drainage work is done.
6. Construction will speed up in September. Please pray for every aspect of the work to proceed according to schedule.
會所盖建进度:
1. 锁墙块沿着南部和东部地界线已放置好,作为永久护墙。
2. 沿Brown 路下水道已於本周开始施工。从星期一至星期五,上午7 时至下午5 时,我们工地
前面是暂时禁止停车区,若有圣徒希望看工程进行,可从後面学校操场观看。
3. 这个星期承包商将开始作现场排水沟的工程。
4. 北部的树和灌木预定在这个月之内清除。
5. 排水工程完成之后,会所的地基工程将开始进行。
6. 工地的进展在9 月将加速。请为建筑的各个方面祷告,盼整个工程能按照时间表进行。
● 工程进行时间表>>