Thursday, August 18, 2011

● Meeting Hall Construction Update as of July 31, 2011 )

 
1. On July 27 and 29, we paid all the development cost charges and sewer works inspection fees to the City, amounting to almost $76,000.

2. A pre-construction meeting will be scheduled this week among the City staff, the sewer construction company, and the engineering consultant, to discuss the procedures for doing the offsite works.
3. August 2 is the earliest date for the building permit to be issued (August 9 at the latest). We should pray for this to take place within this week.
Information regarding the offering pledges for the meeting hall construction ( As of July 24, 2011)
Offering GoalCurrent Accumulated OfferingsCurrent DisbursementCurrent Balance
$4,500,000 (CAD)$2,428,766 (CAD)$1,201,302 (CAD)$1,227,464 (CAD)
Percentage of our Goal Achieved at present
Current Deficit
53.97%
$2,071,234 (CAD)
会所盖建进度:(至2011年7月31日止)
1. 7月27日和29日,我们付了所有的开发成本费和下水道工程驗费,金额约$76,000。
2. 一个施工前的会议将于本周举行,开会成员为市政府职员、下水道建设公司以及提供工程计划、工程图的工程顾问等。
3. 我们的建筑许可证最早可望于8月2日发出(最迟为8/9日),请为此祷告,求主于本周内成全这事。
我们感谢主主宰的安排,在这沉长的过程中,使我们迫切为会所有更多的祷告。但愿我们坚定持续的祷告与奉献 ,使工程从开始到结束不间断地进行。
以下新会所盖建奉献情形: (至2011年7月24日止)
奉献目标
实际收入
实际支出
馀额
$ 4,500,000
$ 2,428,766
$ 1,201,302  
$ 1,227,464
目标达成率
尚缺金额
53.97 %
$ 2,071,234