A video of construction progress
This is the building foundation work on the east side.
Offering Goal | Current Accumulated Offerings | Current Disbursement | Current Balance |
---|---|---|---|
$4,500,000 (CAD) | $2,619,499 (CAD) | $1,264,472 (CAD) | $1,355,027 (CAD) |
Percentage of our Goal Achieved at Present | Current Deficit | ||
58.21% | $1,880,501 |
August 19, 2011: |
---|
• The sewer construction started on Aug. 12 and is expected to be completed by the middle of September. |
• The excavation and foundation work that began on Aug. 16 will last until the first week of October with the pouring of the concrete slab. |
• From the second week of October until the fourth week of November, the concrete tilt panels will be prepared, poured, cured, and erected. |
• The structural steel, metal decking, and roofing will be installed from November until the end of this year. |
Offering Goal
|
Current Accumulated Offerings
|
Current Disbursement
|
Current Balance
|
$4,500,000 (CAD)
|
$2,530,209 (CAD)
|
$1,227,872 (CAD)
|
$1,302,337 (CAD)
|
Percentage of our Goal Achieved at present
|
Current Deficit
| ||
56.23%
|
$1,969,791 (CAD)
|
Offering Goal | Current Accumulated Offerings | Current Disbursement | Current Balance |
$4,500,000 (CAD) | $2,428,766 (CAD) | $1,201,302 (CAD) | $1,227,464 (CAD) |
Percentage of our Goal Achieved at present
|
Current Deficit
| ||
53.97%
|
$2,071,234 (CAD)
|
以下新会所盖建奉献情形: (至2011年7月24日止)
| ||||||||||||||||
|
新会所盖建奉献情形: (至2011年7月17日止)
| ||||||||||||||||
|
新会所盖建奉献情形: (至2011年7月10日止)
| ||||||||||||||||
|