1. Work has
begun on the elevator. It will take 40 days to complete the Installation.
2. BC Hydro
has obtained approved drawings from the City. Work on relocation of the
electric pole
and power supply installation will soon begin.
3. Form work
is in progress for cast-in-place concrete curbs at the perimeter and center of
the
parking
lot. Then pavers will be installed.
4. Interior
work for floor, wall, door, and other finishes, exhaust for the kitchen, and
plumbing for
the
baptistery tub and shower stalls are in progress.
5. Guardrails
will be required for the front patio per building code requirement.
6. Photo on
the right is a view of the main hall looking west towards the central lobby and
upper
floor. Gypsum boards have been installed on
the ceiling and walls.
View from the main hall looking west towards the central lobby and upper floor shows gypsum boards already installed on the ceiling and walls. |
Offering for the meeting hall construction, as of February 12, 2012:
Offering
Goal
|
Current
Accumulated Offerings
($500K Loan from Surrey
And $500K Loan - Burnaby)
|
Current
Disbursement
|
Current Balance
($500K Loan from Surrey and $500K Loan - Burnaby)
|
||
$4,500,000
|
$3,267,242 /
$4,267,242
|
Project Fund
|
Security
Deposit
|
Total
Expenditure
|
–$405,307
/
$594,693
|
$3,462,549
|
$210,000
|
$3,672,549
|
|||
Percentage of our Goal Achieved at present
|
Current Deficit
|
||||
72.61%
|
$1,232,758
|