Tuesday, February 21, 2012

● Meeting hall construction update as of February 17, 2012:


1.           Work has begun on the elevator. It will take 40 days to complete the Installation.
2.           BC Hydro has obtained approved drawings from the City. Work on relocation of the electric pole
               and power supply installation will soon begin.
3.           Form work is in progress for cast-in-place concrete curbs at the perimeter and center of the
              parking lot. Then pavers will be installed. 
4.           Interior work for floor, wall, door, and other finishes, exhaust for the kitchen, and plumbing for
               the baptistery tub and shower stalls are in progress.
5.           Guardrails will be required for the front patio per building code requirement.
6.           Photo on the right is a view of the main hall looking west towards the central lobby and upper
               floor. Gypsum boards have been installed on the ceiling and walls.



View from the main hall looking west towards the central lobby and upper floor shows gypsum boards already installed on the ceiling and walls. 


 Offering for the meeting hall construction, as of February 12, 2012: 


Offering Goal
Current Accumulated Offerings
($500K Loan from Surrey
And $500K Loan - Burnaby)
Current Disbursement
Current Balance
($500K Loan from Surrey and $500K Loan - Burnaby)
$4,500,000
$3,267,242 /
$4,267,242
Project Fund
Security Deposit
Total Expenditure
$405,307 /
$594,693
$3,462,549
$210,000
$3,672,549
Percentage of our Goal Achieved at present
Current Deficit
72.61%
$1,232,758

  