Sunday, February 5, 2012

● Meeting hall construction update as of February 01, 2012



  1. The gas connection and meter installation have been done by Fortis BC
  2. We are working on the cabling and wiring for audio-visual and security/monitoring alarm systems.
  3. Fiberglass insulation is being installed on the perimeter walls.
  4. After all duct works, plumbing, and electrical wiring behind the walls are completed, the gypsum boards will be installed starting on Feb. 6.


Work on the roof (1)


Work on the roof (2)




Video from second floor elevator lobby looking out through the glass panels‏




Insulation is being placed on the wall. Gypsum boards will next be mounted on the steel studs.
(Photo taken from the balcony)  



This photo was taken from the top of the staircase of the front lobby
Brown Road is visible through the glass casing.


Offering for the meeting hall construction, as of January 29, 2012: 
Offering Goal
Current Accumulated Offerings
Current Disbursement
Current Balance
$4,500,000 (CAD)
$3,218,022 (CAD)
Project Fund
Security Deposit
Total Expenditure
$203,484 (CAD)
$2,804,538
$210,000 (CAD)
$3,015,538 (CAD)
Percentage of our Goal Achieved at present
Current Deficit
71.51%
$1,281,978(CAD)