- We will have a site meeting on Monday, Feb 13 to discuss the latest work progress and details.
- The exterior doors are being installed. The security company has begun wiring for security, monitoring, and alarm equipment.
- Drywall gypsum boards are now being installed in all the rooms.
- Backing supports for audio and future video equipment have been installed.
- Audio equipment wiring materials ordered through the electrical contractor have arrived in time for installing in the building.
shows the central lobby viewed from the parking lot. Windows and doors are being installed. |
shows the northeast portion of the main sanctuary, viewed from the
south balcony. Drywall boards on the east wall are completed and are about to be installed on the north wall |
an inside view of the central lobby, looking toward the north. |
The front doors have been installed. The glass panels are fitted with aluminum frames. |
The parking lot is undergoing extensive work before paving, landscaping, and lighting. |
Offering Goal
|
Current Accumulated Offerings
($500K Loan from Surrey) |
Current Disbursement
|
Current Balance
| ||
$4,500,000
|
$3,255,107 /
$3,755,107 |
Project Fund
|
Security Deposit
|
Total Expenditure
|
$240,569 /
$740,569 |
$2,804,538
|
$210,000
|
$3,015,538
| |||
Percentage of our Goal Achieved at present
|
Current Deficit
| ||||
71.51%
|
$1,281,978
|