Sunday, February 12, 2012

● Meeting hall construction update as of February 9, 2012


  1. We will have a site meeting on Monday, Feb 13 to discuss the latest work progress and details.
  2. The exterior doors are being installed. The security company has begun wiring for security, monitoring, and alarm equipment.
  3. Drywall gypsum boards are now being installed in all the rooms.
  4. Backing supports for audio and future video equipment have been installed.
  5. Audio equipment wiring materials ordered through the electrical contractor have arrived in time for installing in the building.

shows the central lobby viewed from the parking lot. Windows and doors are being installed.

shows the northeast portion of the main sanctuary, viewed from the south balcony.
Drywall boards on the east wall are completed and are about to be installed on the north wall

an inside view of the central lobby, looking toward the north.
The front doors have been installed.
The glass panels are fitted with aluminum frames.

The parking lot is undergoing extensive work before paving, landscaping, and lighting.


Offering for the meeting hall construction, as of February 05, 2012:
Offering Goal
Current Accumulated Offerings
($500K Loan from Surrey)
Current Disbursement
Current Balance
$4,500,000
$3,255,107 /
$3,755,107
Project Fund
Security Deposit
Total Expenditure
$240,569 /
$740,569
$2,804,538
$210,000
$3,015,538
Percentage of our Goal Achieved at present
Current Deficit
71.51%
$1,281,978