- The roofing system on the main portion of the building is now complete.
- The roofing for the northwest portion, which will be fitted with glass panels, is scheduled for the coming week.
- The aluminum frames for the windows are being installed.
- A cedar fence is now being erected on the south property line. Another section of fence will be placed on the east property line behind the building.
- The metal decking for the second floor is now complete and concrete pouring will begin on Monday, Dec. 19.
- The parking lot is now being leveled with sand and gravel.
![]() |
Latest photo of the meeting hall's front lobby, showing the main stairs leading to the second floor. (Dec. 16, 2011) |
Offering Goal | Current Accumulated Offerings |
Current Disbursement | Current Balance | ||||||||
$4,500,000 (CAD) | $3,042,646 (CAD) | ProjectFund | Security Deposit | Total Expenditure | $333,989 (CAD) | ||||||
$2,120,657 (CAD) | $588,000 (CAD) | $2,708,657 (CAD) | |||||||||
Percentage of our Goal Achieved at present | Current Deficit | ||||||||||
67.61% | $1,457,354 (CAD) |