This is the future wall panel on the northwest corner of the main sanctuary.
The boxed areas are the openings for the glass windows. After rebars are placed in the spaces between the forms, concrete is scheduled to be poured on October 7.
The longer wood frames are the outer edges of the wall panels. The boxed areas inside are window openings. Reinforcing steel bars will be installed between the wooden forms and concrete will be poured into the spaces. After the concrete cures, the panels will be tilted up to form the walls of the building.
Photo shows workers laying rebars inside the forms in preparation for concrete pouring for the wall panels.
Status on September 30:
- The first layer of asphalt paving was done on September 27. The road works are 85% complete and a payment of $128,000 is due this week.
- Reinforcing bars were laid on Sept. 27, and pouring of the concrete floor slab and polishing of the slab were done on Sept. 28.
- Work on the wall panels began on Sept. 29 with laying out measurements and building the forms for each individual panel.
- The sidewalk construction began on Sept. 30. Foundation work and wiring for street lighting are 50% completed.
Current Status on Material Offerings:
Offering Goal | Current Accumulated Offerings | Current Disbursement | Current Balance |
---|---|---|---|
$4,500,000 (CAD) | $2,715,669 (CAD) | $1,795,960 (CAD) | $919,709 (CAD) |
Percentage of our Goal Achieved at Present | Current Deficit | ||
60.35% | $1,784,331 (CAD) |
No comments:
Post a Comment