- The curb for the road was completed last week. Leveling of the road surface continued.
- Cement pouring was completed to form the concrete retaining walls on the north and west sides of the building.
- A layer of sand and a layer of gravel were paved over the entire floor area to form the subsurface for the pouring of the SOG (slab on grade),which is scheduled for this week.
- The entire month of October is scheduled for the pouring and forming of the tilt panels for the building walls.
- Construction work is proceeding according to schedule. May the Lord supply us continually through the timely offering of the saints.
Pictures of the Current Construction Site:
Current Status on Material Offerings:
Offering Goal | Current Accumulated Offerings | Current Disbursement | Current Balance |
---|---|---|---|
$4,500,000 (CAD) | $2,704,704 (CAD) | $1,765,337 (CAD) | $939,367 (CAD) |
Percentage of our Goal Achieved at Present | Current Deficit | ||
60.10% | $1,795,296 (CAD) |