Sunday, September 25, 2011

● Meeting Hall Construction Update as of September 25, 2011

  1. The curb for the road was completed last week. Leveling of the road surface continued.
  2. Cement pouring was completed to form the concrete retaining walls on the north and west sides of the building.
  3. A layer of sand and a layer of gravel were paved over the entire floor area to form the subsurface for the pouring of the SOG (slab on grade),
     which is scheduled for this week.
  4. The entire month of October is scheduled for the pouring and forming of the tilt panels for the building walls.
  5. Construction work is proceeding according to schedule. May the Lord supply us continually through the timely offering of the saints.


Pictures of the Current Construction Site:










Current Status on Material Offerings:
Offering GoalCurrent Accumulated OfferingsCurrent DisbursementCurrent Balance
$4,500,000 (CAD)$2,704,704 (CAD)$1,765,337 (CAD)$939,367 (CAD)
Percentage of our Goal Achieved at PresentCurrent Deficit
60.10%$1,795,296 (CAD)

No comments:

Post a Comment