2.
Plumbing fixtures have been installed on the
baptismal tub, shower stalls and washrooms.
3.
Onsite landscaping is near completion. Offsite works are 100% complete except
for the final asphalt paving schedule one year from now.
4.
Remaining work on the elevator will be finished by the final week of May.
5.
Deficiencies in the roofing and flooring are being checked and remedied.
6.
The meeting hall is due for city inspection and approval for occupancy after
all paper works are completed. We must pray for all the construction and administrative processes to be concluded by
the end of May and for the building to be turned over to us by early June.
Offering for the meeting hall construction (as of May 20, 2012)
Offering for the meeting hall construction (as of May 20, 2012)
Offering
Goal
|
Current
Accumulated Offerings
($
|
Current
Disbursement
|
Current
Balance
($
|
||
$4,500,000
|
$3,559,062
/
$4,909,062
|
Project Fund
|
Security
Deposit
|
Total
Expenditure
|
–$1,098,045
/
$251,955
|
$4,447,107
|
$210,000
|
$4,657,107
|
|||
Percentage of our Goal Achieved at present
|
Current Deficit
|
||||
79.09%
|
$940,938
|