Wednesday, March 28, 2012

● Meeting hall construction update as of March 22, 2012


1. The offsite work on the power station and pole relocation is proceeding according to schedule.
2. The 6-ft. baptismal tub has arrived and is now being installed.
3. We have decided on installing an island counter in the kitchen for food preparation and service.
4. Painting is almost done in the main sanctuary. Doors and window glazing will be installed next.
5. The elevator company has raised an issue regarding the location of the machine room. Final
    decision will be made this week.

                     Attached are a photo and a short video clip, taken on 
                     March 22, 2012, showing the exterior of the meeting hall.



                             This photo, taken on March 23, shows the west section of the 
                           main sanctuary. Painting has been done, and 8 diffusers for
HVAC have been installed on the ceiling.


Offering for the meeting hall construction, as of March 18, 2012  

Offering Goal
Current Accumulated Offerings
($1.35 M Loan from
Lower Mainland churches)
Current Disbursement
Current Balance
($1.35M Loan from Lower Mainland churches)
$4,500,000 (CAD)
$3,384,877
 /$4,734,877
Project Fund
Security Deposit
Total Expenditure
–$624,862 /$725,138
$3,799,739
$210,000
$4,009,739
Percentage of our Goal Achieved at present
Current Deficit
75.21%
$1,115,123